Date | Event |
---|---|
September 1, 1994 | Opening ceremony for the pipeline construction start |
December 21, 1994 | 50% of the pipeline route welded |
April 1, 1995 | Commencement of pipeline stress tests |
April 20, 1995 | End of pipe delivery |
April 27, 1995 | Erection of first electric station cabins along the pipeline |
May 12, 1995 | End of pipeline welding (except for interconnections) |
May 31, 1995 | Commencement of the optical cable laying |
June 22, 1995 | Delivery of first ball valves |
June 26, 1995 | Commencement of pipeline calibration using intelligent pig |
July 27, 1995 | First ball valves placed in the pipeline |
August 14, 1995 | Commencement of completion of telemetry and Technological Processes Management System in electric station cabins and valve chambers |
August 31, 1995 | Last joint welded |
December 15, 1995 | Filling of the IKL pipeline with crude oil |